Di-ammonium Phosphate Plant (DAP), Ras Az Zawr

Industrial & Mechanical

Saudi Arabian Mining Company (Ma’aden)/Dragado Industrial, S.A.



Nesma & Partners was the Main Subcontractor to Dragados for the total construction of Di-ammonium Phosphate Plant (DAP).   


Our scope of work (SOW) included construction of all Civil and Infrastructure works, Heavy foundations, Buildings, Structural steel erection, Mechanical / Equipment erection, Heavy lift, Electrical, Instrumentation, Painting, Insulation, including assistance to pre-commissioning and final commissioning.


SOW also included construction of a Temporary Camp and Site Office facilities for use by the designated personnel of Dragados & Ma’aden. The temporary facilities include portable buildings of accommodation, offices, common support facilities, recreation and sports facilities, access roads, landscaping etc.