Waste Water Environmental Protection, Abqaiq

Electro - Mechanical

Saudi Aramco 



The scope of work performed under this contract included installation of new equipment and approximate 17 km of pipeline to transfer Abqaiq Plants industrial water from Three Phase Separator (TPS) area to the existing Three Injection Wells ABQ-273, 320 and 615 located near Abqaiq GOSP-5.


Work under this contract involved field installation of booster and injection pumps, spurge system new pipeline, pipelines between wells and 148,000-barrel surge tank, installation of new chemical injection equipment to inject corrosion/scale inhibitors, biocides and waste water polymers and all associated civil and mechanical works.